| |
A new financing horizon?
Despite the enormous promise of
offshore wind, projects have struggled to
attract financing. Shane Woodroffe
and Mark Dennes ask why, and
explain how the wind is changing
The potential for offshore wind is huge. Properly developed, offshore
wind projects address local community and environmental concerns,
and can help to circumvent many of the barriers that face wind energy
development onshore. And, with governments struggling to deliver
on their renewable energy and carbon reduction goals – not to mention
energy security – moving offshore is seen as a path to meeting those
targets.
The European Wind Energy Association (EWEA) predicts that Europe
alone has the potential to install more than 70GW by 2020, equivalent
to almost twice current installed wind capacity in Europe. The US
Department of Energy, meanwhile, estimates the potential of offshore
wind at up to 900GW.
But the capital needed to develop wind farms offshore is enormous,
and substantially greater, like for like, than for those onshore.
At around £1.5 million ($2.8 million)/MW, today’s estimate of the
all-in offshore installation cost, meeting the EWEA’s 70GW target
will require more than £100 billion of investment, or some £7 billion/year.No
wonder finance providers are so eager to explore investments in
the sector.
However, the arrival of bankable offshore wind farm projects has
been a long time coming. Wind farms have been operating offshore
since 1991, but financiers have, to date, given them a wide berth
– and those that have been built have almost all been financed on-balance
sheet, typically by large utilities, rather than by tapping the
commercial bank and project finance markets. Onshore wind is cheaper,
simpler and proven – why should we be moving the turbines offshore?
A fair wind
It is often argued that there is more plentiful wind resource offshore.
Certainly there are fewer topographical effects, but wind farms
on hills in Scotland (with load factors – ie, the percentage of
a year’s full output that they actually generate – of up to 51%1)
are yielding more energy than some of the Danish offshore wind farms
in more sheltered waters (with c. 30% load factors2).
However, prominence on the tops of hills is one of the main reasons
why wind farms are being driven offshore. Hilltops are both limited
in number and often vociferously protected by nearby residents.
Furthermore, offshore sites provide the possibility for increasingly
large-scale developments, with planned wind farms in the hundreds-of-megawatts
range now becoming the norm.
But higher costs…
Detractors of offshore wind often point to the increased costs,
which must eventually filter through to our electricity bills. It
is not simply the extra cost of trying to build up to 20 kilometres
offshore in 20 to 30 metres of, at times, treacherous waters. The
complexity of offshore construction is further exacerbated by the
necessary use of specialist vessels in a restricted April to September
weather window, and the additional installation of a subsea connection
cable to bring the electricity back to shore.Current estimates show
that electricity generated offshore is some 1.5–2 times as expensive
as that coming from onshore wind sites, at around £82/MWh compared
to about £54/MWh3.
"The introduction of commercial lending to the offshore
wind sector will be a huge boost for the industry and should
speed the installation of megawatts offshore"
|
A sizeable element of the offshore wind construction costs is
the foundation and tower structure, at around £240,000/MW compared
to £115,000/MW for onshore wind4.The foundations are typically either
driven steel piles of up to five metres in diameter for deeper water
sites, or large 17 metre-wide, 2,000-tonne concrete gravity-based
structures that sit on the (pre-prepared) sea-bed in shallow water
sites.
Given the restrictive installation time window, and the increased
cost of erecting turbines offshore, developers tend to opt for the
largest size turbine possible.The wind industry has come a long
way in the past five years, with a move towards ‘multi-megawatt’
turbines. Onshore turbines today are often in the 1.5MW to 2.5MW
size, but the move offshore is seeing manufacturers striving for,
and achieving, even larger sizes.
The most recent offshore wind farms have been built using the 3MW
turbine produced by Vestas of Denmark (Barrow and Kentish Flats,
both off the coast of the UK), with the next announced UK project
(Burbo Banks) going for the 3.6MW unit produced by Siemens.German
turbine manufacturer REpower has been testing a 5MW model at Brunsbüttel
on the coast of Germany for over a year now, and will be installing
two of these 900-tonne behemoths, rising some 107 metres above the
water, at the Beatrice wind farm in the North Sea, 22 kilometres
off the northeast coast of Scotland in the Moray Firth.
The impact of wind farms on the environment has always split public
and official opinion and offshore wind farms, albeit less visible
when located several kilometres offshore, are no different. And,
in addition to the bird, plant and animal life concerns that onshore
wind needs to address, offshore wind also has to meet shipping and
coastguard requirements. Planning and permitting is rigorous, as
evident by the time taken to complete studies and consultation before
lodging a permit for planning approval. In the UK, this typically
takes a minimum of two years.
…and some problems
Unsurprisingly, construction of offshore wind farms has not been
without its problems.The most frequently cited case is the 160MW
Horns Rev wind farm, located 14–20 kilometres off the coast of Denmark.
Vestas, which installed 80 of its 2MW units at this deep-water
site, had to take down each nacelle (the ‘box’ that sits at the
top of the tower and houses the gearbox, generator and supporting
ancillary items) and transport them back to shore to carry out repairs
– replacing components that had been expected to last significantly
longer. Many in the industry, however, saw this as positive with
Vestas standing by its commitment to offshore wind and, within four
months, all 80 nacelles had been taken down, repaired and were back
up and generating.
Other offshore wind farms have had similar, but less costly, stories
of delays and reduced output, although many have eventually achieved
their initially predicted performance. Serial failures of nacelle
components are a financier’s worst nightmare. This slightly wobbly
track record for offshore wind, plus the drive of the manufacturers
to rush out newer and bigger turbines that have not yet been proven,
are the main reasons why banks have not yet provided non-recourse
financing for offshore wind farms.
Operational questions
The other big unknown for financiers and investors alike is long-term
operational performance. While offshore wind farms have been in
operation since 1991, the newer models in the hazardous North Sea
have less of a track record.To capture the wind when it does blow
requires each turbine in the wind farm to, in the jargon used by
engineers and capital providers, be ‘available’.
Consistent availability figures of 98% have been achieved onshore,
but offshore it is less certain that even the predicted 95–96% availability
levels can be achieved. This is due to adverse weather that can
stop access, perhaps for days at a time, to turbines to fix a fault.
Every hour lost through no availability is the loss of an hour of
valuable generation and revenues that are needed to give returns
on the invested capital.
Progress to date
As a consequence of these factors, progress to date has not been
spectacular. Last year,90MW of offshore wind capacity was installed,
compared to 11,441MW of onshore wind capacity. In 2004, the figures
were 60MW and 7,967MW, according to the Global Wind Energy Council.
Although there are almost 800MW of projects that have been consented
in the UK alone, installation of offshore wind farms has recently
been hampered by rising steel prices and limited turbine supply
as manufacturers, wary of the risks of offshore wind construction,
and still smarting from losses, refocus on the onshore market.
Build-out rates are likely to continue to lag behind the predicted
installation rates, but 2006 is shaping up to be a watershed in
offshore development. The 120MW Q7 project located off the coast
of the Netherlands and the 21.6MW first phase of the Thornton Bank
project, under development by C-Power off the coast of Belgium,
are fighting it out to be the first project-financed offshore wind
farm. No matter who crosses the project finance finish line first,
the introduction of commercial lending to the offshore wind sector
will be a huge boost for the industry and should speed the installation
of megawatts offshore.
Europe leads
The countries leading the development of offshore wind are the
UK, Ireland, Germany, France, the Netherlands, Belgium, Spain and
Portugal.To encourage overall renewable energy generation – which
tends to be more expensive than fossil fuel-derived power – EU countries
have introduced a variety of support regimes, typically feed-in
(fixed price) tariffs or a quota system typically linked to tradable
‘green’ certificates (whose price is not necessarily fixed).
These support mechanisms have rapidly advanced the installation
of onshore wind, but additional measures have had to be employed
to stimulate the growth of offshore wind. For example, in Belgium,
electricity supply companies are obliged to pay €107/MWh for power
from offshore wind farms, compared to as low as €65/MWh for its
onshore equivalent. Similarly, France’s offshore feed-in tariff
was recently raised to €130/MWh.
To date, Denmark has seen the most wind farms installed offshore,
with some 409MW installed and the 200MW Horns Rev II and 200MW Rodsand
(Nysted II) consents now awarded, with construction expected to
start in 2007 and 2008 respectively5.
Going forward, the UK, given some of the best wind resources in
Europe, is likely to provide the majority of new offshore wind projects.
The UK offered £10 million in grants to encourage the development
of its first round offshore sites, while the Energy Review has proposed
that offshore farms receive more Renewable Obligation Certificates
(the UK’s tradable green certificates) per MWh for second round
offshore projects.
German offshore projects receive the same feed-in tariff as for
onshore windfarms but over 12 years, as opposed to five for onshore
projects.
North America progress
The US as a whole has abundant acreage onshore, with large pockets
of windy rural lands, most of which are found in the sparsely populated
areas west of the Mississippi. With slightly more than half the
country’s population living in the coastal zones, however, it would
be necessary to upgrade the transmission grid to allow for the interstate
transfer of large amounts of wind power back to the population centres.This
would require huge investment, preceded by lengthy regulatory and
legislative approvals.
Tapping the strong winds offshore, which are much closer to urban
load centres, is seen as an alternative to these transmission challenges.
There are at least 15 offshore wind farms in development in the
US including the 130-turbine, 420MW Cape Wind project in Nantucket
Sound. Expected to be the first US first offshore development, Cape
Wind has endured years of public and political opposition. With
opponents further claiming that Cape Wind’s 247-foot-tall turbines
would kill migrating birds and could threaten the region’s lucrative
tourist industry, the project still faces significant challenges
even if it survives its current regulatory review which is ongoing
in Washington. Currently, US offshore wind does not receive any
additional support over and above the normal renewable power production
tax credit.
Conclusion
As stated at the outset, the arrival of bankable offshore wind
farm projects has been a long time coming.To date, projects have
been built on balance sheet, and financiers have shied away from
the risks involved.With notable setbacks both very visible and well
documented, many financiers believe they were right to wait until
now before dipping their collective toes in the offshore water.
Fortis has watched this market closely and, having already advised
three offshore projects in preparation for project financing, will
be one of those most certainly getting its feet wet.
Shane Woodroffe is the London-based director of renewable energy,
and Mark Dennes is a New York-based vice president, at Fortis Bank.
E-mails: shane.woodroffe@fortis.com,
mark.dennes@us.fortis.com
The introduction of commercial lending to the offshore wind sector
will be a huge boost for the industry and should speed the installation
of megawatts offshore
1 Burradale Wind Farm, Shetland (DTI & Garrad Hassan and Partners)
2 Middelgrunden Offshore Wind Farm, off Copenhagen
(DTI & Garrad Hassan and Partners)
3 UK Energy Review 2006
4 Source: New Energy Finance and Garrad Hassan and Partners
5 Offshore Wind: Implementing a New Powerhouse for Europe, Greenpeace,
2005.
|